Planning permission and building regulations are not the same thing.

One decides whether you may build it. The other decides how it must be built. Most projects need both, and they run in a particular order.

A white and navy shaker kitchen with an island.

Planning permission: may you build it?

Planning is the local planning authority's decision on whether a development is acceptable in its place: its size, its height, its appearance, its effect on neighbours and the street, and the use the building is put to. Many domestic projects fall under permitted development and need no application, subject to the limits described in planning permission for an extension. Everything else needs an application, and a listed building needs listed building consent as well. Where no application is needed, a lawful development certificate puts that in writing.

Building regulations: how must it be built?

Building regulations are national standards for the construction itself, set out in the Approved Documents. They cover the structure, fire safety, resistance to moisture, sound, ventilation, drainage, heat-producing appliances, stairs and guarding, energy efficiency, access, glazing and electrical safety. They apply whether or not planning permission was needed. An extension that is permitted development still needs building regulations approval; so does a loft conversion, a structural opening, a new bathroom that changes the drainage, and most electrical work in a kitchen or bathroom.

You choose who checks the work: the local authority's building control department, or a private registered building control approver. Both inspect at stages and both issue the completion certificate.

Two routes to approval

  • Full plans. Detailed drawings and calculations are submitted and checked before work starts. You can expect a decision within five weeks, or two months if you consent to the longer period. Once the work is finished and inspected, the completion certificate usually follows within eight weeks. This is the route for anything with structure in it.
  • Building notice. A short notice of the intention to carry out work; you may start two days after it is submitted. Nothing is checked in advance, so mistakes are found on site by the inspector. It is only for smaller projects.

The parts that decide the drawings

For an extension, a loft or a refurbishment, a handful of the Approved Documents do most of the work. Part A, structure: the beams, the foundations, the openings. Part B, fire: escape routes, fire doors, alarms, and the 4.5 metre rule that turns a loft stair into a protected route. Part C, moisture and ground: damp-proof courses and membranes. Part F, ventilation: extract in kitchens and bathrooms, background ventilation elsewhere. Part K, stairs and guarding. Part P, electrical safety, usually met by using a registered competent person who self-certifies the work. And Part L, energy.

Part L sets limiting U-values for new elements added to an existing house. Under the 2021 edition of Approved Document L, which has applied since 2022, a new wall in an extension must achieve 0.18 W/m²K, a new roof 0.15, a new floor 0.18, and new windows 1.4. Those numbers decide the wall build-up, the insulation depth and the glazing specification before the room is drawn in any detail.

The order they run in

  1. The permitted development check, or the planning application. Nothing else is worth spending on until the planning question is settled.
  2. The building regulations drawings and structural calculations, submitted as full plans.
  3. The party wall notices where the work touches a boundary, timed so that the notice periods end before the start on site.
  4. The build, with the inspections at each stage.
  5. The completion certificate, which goes in the file with the drawings and the finishes schedule. A buyer's solicitor will ask for it.

One set of drawings

On a design and build contract the same team draws for planning, for building control and for the price, so the drawings that get approval are the drawings that get built. That is the point of the model, and it is why the studio's process puts the drawings before the price. The building regulations that matter most under a roof are set out in loft conversion types and rules.

Sources

Rules and figures checked in September 2026 and given for England unless stated. They change; check the current wording with the local authority before relying on them.

Questions

Asked about this.

Every question
If my extension is permitted development, do I still need building regulations approval?

Yes. Permitted development only answers the planning question. Building regulations apply to almost all building work regardless: the foundations, the structure, the insulation, the drainage, the electrics, the fire safety and the glazing are all checked by a building control body, and you receive a completion certificate at the end.

Should I use a full plans application or a building notice?

Full plans for anything with structure in it. The building control body checks the drawings before you start, so a problem is found on paper rather than on site, and you receive a decision within five weeks, or two months if you agree to it. A building notice lets you start two days after submitting it, but nothing is checked in advance, and it is meant for smaller work.

Who does the building control inspections?

Either the local authority's building control department or a private registered building control approver; you choose. Whoever it is visits at set stages, typically the excavations, the foundations, the damp-proof course, the drains, the structure and the insulation, and again at completion before issuing the certificate.

See also

Rooms and services beside this one.

  1. Process

    Brief, drawings, price, build, keys: where each approval sits.

  2. Planning permission for an extension

    The permitted development limits.

  3. Loft conversion types and rules

    The building regulations that apply under the roof.

Start a project

Tell us about the room.

A few lines about the site and what it needs to become is enough. A person at the studio reads every message.

Working across the United Kingdom

Please tell us your name.
Please enter an email address we can reply to.
A line or two about the project, and the town or postcode, helps us reply well.

The message did not send. Call us on 07368 632199, email info@luminadesignbuild.co.uk, or try again in a moment.

Your details are used to reply to you and for nothing else. No newsletters. How we handle your information.

Thank you.

Your message is with the studio. We will reply by email, and if you left a number we may call.

Call Us Start a Project