The roof you have decides the conversion you can build. Then permitted development decides its size, and building regulations decide its stair, its floor and its fire escape.

A finished loft bedroom with rooflights, a white balustrade at the stair and a sofa under the eaves.

Rooflight

The conversion that keeps the roof as it is. Rooflights are set into the existing slope, the floor is strengthened, the stair goes in and the room is insulated. It involves the least structural work of the four and rarely needs planning permission, but it only works where the roof already has the height and the pitch to give a usable room.

Dormer

A box that projects from the roof slope, usually at the rear, with a flat roof and vertical walls. It adds headroom and floor area where the slope would otherwise have taken it. A full-width rear dormer is the most common loft conversion on terraced and semi-detached houses; an L-shaped dormer runs a second box over the back addition of a Victorian or Edwardian house.

Hip-to-gable

For a hipped roof, the kind that slopes in on the side as well as the front and back, common on semi-detached houses and end-of-terrace houses. The sloping side is built up into a vertical gable wall, which recovers the space the hip took away. It is usually combined with a rear dormer, so the loft gains volume on two sides at once.

Mansard

The rear slope of the roof is rebuilt at a steep angle, close to vertical, with a flat top, so that the loft becomes almost a full storey. It gives the most floor area and the most conventional room. Because it changes the shape of the roof, it usually needs planning permission rather than falling under permitted development.

What permitted development allows

In England, Class B of the General Permitted Development Order lets you enlarge a roof without a planning application, on a house, if all of the following hold:

  • The added volume is no more than 40 cubic metres on a terraced house or 50 cubic metres on a detached or semi-detached house. Earlier roof additions count against the allowance.
  • Nothing extends beyond the plane of the existing roof slope on the principal elevation that fronts a highway.
  • Nothing is higher than the highest part of the existing roof.
  • The enlargement is set back at least 20 centimetres from the original eaves, measured along the roof slope, except for a hip-to-gable.
  • Materials are similar in appearance to the existing house.
  • Side-facing windows are obscure-glazed, and any opening part is at least 1.7 metres above the floor.
  • No verandas, balconies or raised platforms.

Houses on Article 2(3) land, which includes conservation areas, national parks and areas of outstanding natural beauty, do not have these rights and need an application. Flats have no permitted development rights for roof extensions at all. As with an extension, a lawful development certificate from the council is worth having even when the work is permitted.

What building regulations require

Every loft conversion needs building regulations approval, whether or not it needs planning permission. The main points:

  • Structure. The existing ceiling joists were sized to hold a ceiling, not a floor. New floor joists are fitted, usually spanning between new steel beams, and the roof structure is checked and often re-supported where purlins or struts are removed to make the room.
  • Fire. A two-storey house with a converted loft becomes a three-storey house. Once a floor is more than 4.5 metres above ground level, the stair becomes a protected escape route with 30 minutes of fire resistance, the doors from habitable rooms onto it are fire doors, and mains-powered, interlinked smoke alarms are fitted on every storey. An open-plan ground floor needs either a new partition to enclose the stair or a sprinkler system.
  • Stairs. A fixed stair, not a ladder. The usual headroom of 2 metres may be reduced on a loft stair to 1.9 metres at the centre of the flight and 1.8 metres at the side.
  • Insulation. The new roof, walls and floor must meet the current limiting U-values, which decide the depth of insulation between and over the rafters.
  • Sound. Where the loft sits over a neighbour's, or the conversion creates a separate dwelling, the sound insulation rules apply.

A conversion on a terraced or semi-detached house nearly always bears its new beams on the party wall, which means two months' notice to the neighbour under the Party Wall Act. The two routes for building regulations approval, full plans or a building notice, are compared in planning permission versus building regulations.

How the studio draws one

The stair, the height and the structure are drawn before anything is priced, because they decide whether the room is worth having. The same drawings serve planning, building control and the party wall notice, and the team that drew them builds the conversion. The service is described on the loft conversions page.

Sources

Rules and figures checked in September 2026 and given for England unless stated. They change; check the current wording with the local authority before relying on them.

Questions

Asked about this.

Every question
How much headroom do I need for a loft conversion?

As a rule of thumb, builders look for about 2.2 metres from the top of the existing ceiling joists to the underside of the ridge before converting. The new floor takes some of that, and the finished room needs to be usable. On the stair, the regulations allow 1.9 metres of headroom at the centre of the flight and 1.8 metres at the side, which is lower than the 2 metres required elsewhere.

Do I need planning permission for a rear dormer?

Often not. A rear dormer is usually permitted development, provided the added roof volume stays within 40 cubic metres on a terraced house or 50 cubic metres on any other house, it is set back at least 20 centimetres from the eaves, it is no higher than the existing roof and it does not face a highway. Houses in conservation areas and similar designated land do not have these rights.

Why does a loft conversion change the fire rules for the whole house?

Because it adds a storey. Once a floor sits more than 4.5 metres above ground level, an escape window is no longer enough. The stair from that floor to the outside becomes a protected route: 30 minutes of fire resistance, fire doors on the rooms that open onto it, and mains-powered, interlinked smoke alarms on every floor.

See also

Rooms and services beside this one.

  1. Loft conversions

    A bedroom and a bathroom under the roof, drawn and built by one team.

  2. The Party Wall Act

    Steel beams bearing on a shared wall need two months' notice.

  3. Planning permission and building regulations

    Full plans or a building notice, and the completion certificate.

Start a project

Tell us about the room.

A few lines about the site and what it needs to become is enough. A person at the studio reads every message.

Working across the United Kingdom

Please tell us your name.
Please enter an email address we can reply to.
A line or two about the project, and the town or postcode, helps us reply well.

The message did not send. Call us on 07368 632199, email info@luminadesignbuild.co.uk, or try again in a moment.

Your details are used to reply to you and for nothing else. No newsletters. How we handle your information.

Thank you.

Your message is with the studio. We will reply by email, and if you left a number we may call.

Call Us Start a Project